Warning: the inspector flagged our fire caulk on a Tuesday and we lost 3 days
Last week we were wrapping up a tenant buildout in Columbus and the inspector walked the third floor and tagged every penetration where we used the wrong caulk. We had to cut out and redo 47 sleeves because the spec called for an intumescent sealant and our sub grabbed the regular stuff from the truck. That put us behind on the ceiling grid and the GC is now asking why my crew was standing around for two days. How do you all keep the right sealant straight when there are five buckets on site?