Missing punch list items in walkthroughs are costing me 2 extra site visits
Last month in Austin I did a final walkthrough on a retail build and found the caulking at the storefront was never done. The GC claimed it was in the original scope but his punch list only had electrical and drywall. I've seen this on 4 of my last 6 projects, always the small items like sealants or threshold plates that fall through. It adds a day of travel each time plus rescheduling my crew. How do you guys handle verifying the full spec list before signing off on a walkthrough date?
1 comments
Log in to join the discussion
Log In1 Comment
adam_lewis16d ago
The caulking at the storefront thing reminds me of a job where we found the threshold plate in a box in the back office after the owner already signed off. I started taking photos of every single item on the spec list before we even set a walkthrough date, and it’s cut my return trips way down. It’s boring work but beats burning a whole day driving back to fix a two dollar piece of metal.